Telangana Dy CM Bhatti seeks Centre’s nod for Rs 25,096-cr power sector projects within 60 days

New Delhi, Nov 27 (TNT)) : Telangana Deputy Chief Minister and Energy Minister Mallu Bhatti Vikramarka on Friday urged the Centre to approve pending power sector project proposals worth ₹25,096 crore within 60 days and extend financial support for strengthening the State’s power generation, transmission and distribution infrastructure.
Participating in the Conference of State Power Ministers chaired by Union Power Minister Manohar Lal in New Delhi, Bhatti sought Central assistance for pumped storage projects, transparency in inter-state power transmission charges and extension of the waiver on transmission charges for renewable energy projects until March 2030.
He said Telangana had submitted Detailed Project Reports (DPRs) worth ₹25,096 crore to the Power Finance Corporation on May 27 under the Revamped Distribution Sector Scheme (RDSS), covering smart meter installation, reduction of distribution losses and modernisation of the power distribution network. However, the State had received only ₹72 crore in budgetary support so far.
He urged the Centre to approve the pending proposals within 60 days and extend the implementation deadline until March 31, 2028, while noting that billing efficiency of the State’s distribution companies had improved over the past three years.
Welcoming the Union Cabinet’s decision to provide ₹14,500 crore as viability gap funding (VGF) for 92 GWh of electricity storage capacity, Bhatti requested that the benefit be extended to pumped storage projects undertaken by State-owned power generation companies and public sector undertakings.
He sought VGF of ₹1 crore per MW for such projects and expedited approval for the Kallur Pumped Storage Project proposed by TGGENCO.
He also sought Central financial assistance for Telangana’s proposed 2,000 MWh battery energy storage projects, for which the State had initiated the tendering process.
On inter-state transmission charges, Bhatti said Telangana supported the General Network Access (GNA) framework but expressed concern over fluctuations in charges.
Despite its network access entitlement remaining unchanged at 5,801 MW, the State was charged ₹195 crore in October 2025 and ₹145 crore in November 2025, he said.
He urged the Centre to disclose the monthly State-wise calculation of transmission charges, introduce an annual per-MW tariff mechanism and avoid retrospective revisions and additional charges.
Seeking priority for southern power transmission infrastructure, he called for full national status for the 6,000 MW Raigarh-Pugalur-Thrissur HVDC transmission system and early approval of Green Energy Corridor projects with a capacity of 23,480 MVA.
He also sought inter-state transmission project status for the proposed 400 kV double-circuit line from Sedam in Karnataka to Parigi in Telangana and the 765/400 kV Maheshwaram-II substation, with their costs shared at the national level.
The Deputy Chief Minister requested extension of the phased waiver of inter-state transmission charges for renewable energy projects until March 31, 2030, as several projects at the tendering stage were expected to become operational only from February 2029. The existing waiver is scheduled to end on June 30, 2028.
Referring to the impact of El Niño, he said hydropower generation in September 2026 declined by around 20 per cent compared to the corresponding period last year, while coal-based generation increased by 13.3 per cent.
The country also recorded a power shortage of approximately 560 million units during the month, he added.
With electricity demand expected to increase during the coming summer, Bhatti urged the Centre to ensure the availability and operation of gas-based power plants across the country from February 1 to April 30, 2027.
He sought necessary directions under Section 11 of the Electricity Act, 2003, and coordination with the Union Ministry of Petroleum and Natural Gas to ensure adequate gas supplies.
He suggested that the additional costs arising from such arrangements be shared through a common mechanism instead of being imposed on individual States.
Bhatti reiterated the need for Central support to enable Telangana to meet its growing electricity requirements and improve the efficiency of its power distribution companies.
Special Chief Secretary Vikas Raj and TG TRANSCO CMD and Deputy Chief Minister’s Special Secretary Krishna Bhaskar also participated in the conference.