Main breakthrough achieved in 6.59-km tunnel of Rishikesh-Karnaprayag rail project

Rudraprayag (Uttarakhand), Nov 27 (TNT) : Indian Railways on Friday achieved the main tunnel breakthrough in Tunnel-14, measuring 6.59 km, of the Rishikesh-Karnaprayag Rail Project in Rudraprayag district of Uttarakhand.
The breakthrough connected two excavated sections of the tunnel, comprising 4.7 km from Portal-1 at Sumerpur and 1.79 km from Portal-2 at Marora, the Railways said in a release.
The excavation involved several engineering challenges, particularly at Portal-1, where a 110-metre stretch of the triple-track tunnel passed through loose soil beneath inhabited areas, with only 20-30 metres of soil and rock cover.
Specialised techniques, including pre-excavation and multi-drifting, were adopted to ensure safe excavation.
At Portal-2, the slope was stabilised using micropiles extending 30-35 metres deep, rock bolts measuring 15-20 metres and consolidation grouting. These measures facilitated the launch of the main tunnel excavation in March 2024 after resolving ground settlement issues at Marora and matters relating to land and house acquisition.
Around 100 metres of mechanical excavation was carried out at Portal-2. Controlled blasting was undertaken near both portals strictly during daytime hours to ensure the safety of nearby settlements.
Specialised ventilation systems were installed along the 4.7-km excavation stretch from Portal-1 to ensure adequate fresh air supply and regulate temperature inside the tunnel.
The breakthrough marks a significant milestone in the construction of the Rishikesh-Karnaprayag railway project, which is expected to improve connectivity to the hill regions of Uttarakhand, facilitate pilgrimage and tourism and accelerate regional development by providing better access to important destinations in the state.
TNT KS