Surat-Bilimora section of Bullet Train corridor energised
Hyderabad, Nov 21 (TNT) : The Overhead Equipment (OHE) system on the 50-km Surat-Bilimora section of the Mumbai-Ahmedabad Bullet Train corridor has been successfully energised, marking a significant milestone in India’s first high-speed rail project.
The energisation was completed on November 20, covering both Up and Down lines on the elevated section, a release said on Saturday.
The energisation process will be carried out progressively in smaller sections under the supervision of technical teams to ensure safety and compliance with prescribed procedures.
The development will facilitate further testing activities on the corridor.
The Mumbai-Ahmedabad high-speed rail project is equipped with an advanced 2 × 25 kV Overhead Traction System.
The 508-km corridor will have 14 strategically located Traction Substations (TSS), which will receive power from the national grid and supply electricity to the overhead traction system.
The first traction substation at Bilimora in Gujarat’s Navsari district has completed installation works in the control panel, changeover switch, transformer and circuit breaker buildings.
The traction substations in Gujarat will receive power from the 220 kV Ambetha Grid Substation of Gujarat Energy Transmission Corporation Limited (GETCO). The entire electrical network will be monitored through a centralised control centre to ensure safe and reliable operations.
The Surat-Bilimora section includes bridges across four rivers and a steel bridge over National Highway 53.
The elevated viaduct is also equipped with approximately 94,000 noise barriers to minimise noise impact on surrounding areas.
With the energisation of the overhead electrical system, residents, commuters, construction workers and members of the public have been advised not to approach or touch the electrical installations or undertake any unauthorised work near the alignment.