Yadadri fifth unit to begin commercial operations in December, Telangana targets 4,000 MW generation

Hyderabad, Nov 17 (TNT) : Telangana’s 4,000 MW Yadadri Thermal Power Station (YTPS) is expected to achieve its full installed generation capacity by December with the fifth 800 MW unit scheduled to commence commercial operations, strengthening the state’s power availability ahead of the Rabi season.

Four of the five 800 MW units at the plant in Damaracherla mandal of Nalgonda district are already generating electricity and supplying it to the state.

The fifth unit was synchronised with the grid on October 20 and is being readied for commercial operations, an official release said on Tuesday.

The Telangana Power Generation Corporation Limited (TGGENCO) has initiated a comprehensive action plan to resolve technical issues in the coal-handling system and ensure uninterrupted fuel supplies for operating all five units at full capacity.

According to official sources, four coal-feeding lines have been restored, with each having a capacity to handle 800 tonnes of coal per hour, taking the total coal-handling capacity to 3,200 tonnes per hour.

The restoration measures were taken following inspections by a high-level team of BHEL and TGGENCO officials led by Special Chief Secretary to the Energy Department Vikas Raj and TGGENCO Chairman and Managing Director Dr S Harish, following directions from Chief Minister A Revanth Reddy and Deputy Chief Minister Bhatti Vikramarka.

Meanwhile, the state government has made arrangements to ensure adequate coal supplies from multiple sources.

Three to four coal rakes are being transported daily from the Naini coal mine operated by Singareni Collieries Company Limited (SCCL), with 4.26 lakh metric tonnes already supplied to the plant.

Agreements have also been finalised for procuring 4.6 lakh tonnes of coal from Mahanadi Coalfields Limited (MCL) and South Eastern Coalfields Limited through the Window-II auction mechanism.

Fuel Supply Agreements were concluded on November 4, and transportation has commenced.

In addition, the Standing Linkage Committee has approved an annual coal supply of 7.71 million tonnes from MCL and Eastern Coalfields Limited (ECL), subsidiaries of Coal India Limited, for two units of the plant.

The arrangement is expected to provide long-term assurance of coal availability and quality.

The measures have contributed to improved power generation, with Telangana recording an all-time high generation of 6,088 MW on November 11. Yadadri Thermal Power Station alone contributed 2,754 MW on that day, officials said.

As part of the phased restoration of the coal-handling system, TGGENCO will undertake maintenance of the first coal-feeding line from November 18 to 24.

The other three lines will continue to operate during the period.

TGGENCO plans to maintain generation of around 2,000 MW through four units during the maintenance period. If required, generation will be regulated at 1,800 MW in coordination with the State Load Despatch Centre (SLDC), officials said.

The maintenance works will be jointly undertaken by BHEL and TGGENCO with the support of PMPL, BTL and L&T.

The works will cover conveyor belts, feeders, crushers, stackers, reclaimers and other associated equipment. BHEL will subsequently demonstrate a coal-handling capacity of 2,500 tonnes per hour.

The project had faced delays due to the COVID-19 pandemic, forest clearances, railway land-related issues and environmental permissions.

Construction resumed in February 2024 following fresh environmental impact assessment studies and public hearings.

With the fifth unit nearing commercial operations and coal supply arrangements strengthened, TGGENCO is gearing up to achieve the full 4,000 MW generation capacity at Yadadri during the upcoming Rabi season.